Steel Slabs as Breakbulk Cargo
Steel slabs are semi-finished steel: heavy rectangular blocks cast for further rolling into plate and coil. Each slab is lifted, stowed and secured as an individual unit, so a slab cargo is chartered as breakbulk even when the parcel is the size of a bulk carrier cargo.
This practical case, based on a voyage-chartering structure for 50,000 MT of slabs from Paradip, India, to Diliskelesi, Türkiye, shows which technical and contractual points decide whether a vessel and a fixture work for the cargo.
Cargo Particulars
Example cargo particulars:
- Cargo:
- Steel slabs
- Quantity:
- 50,000 MT ±5% CHOPT
- Max unit weight:
- 28 MT
- Max width:
- 1,550 mm
- Max length:
- 10.8 m
- POL:
- Paradip, India
- POD:
- Diliskelesi, Türkiye
- Loading rate:
- 8,000 MT/day
- Discharge rate:
- 8,000 MT/day
- Vessel gear:
- minimum 4 × 30 MT SWL
Slabs are lifted piece by piece, so the heaviest unit, not the average, sets the requirement for the cranes and the lifting gear.
Why DWT Alone Is Not Enough
On paper, a 50,000 MT parcel points to a Supramax or Ultramax bulk carrier. Deadweight, however, says nothing about whether the ship can lift, stow and land 28 MT pieces safely. Hold configuration, hatch openings, tank-top strength and cargo gear decide suitability.
In this case the contemplated vessel is a geared bulk carrier or general cargo vessel of less than 20 years of age, classed with an IACS member and entered with an International Group P&I Club.
Hold and Tank-Top Requirements
Slabs up to 10.8 m long and 1,550 mm wide must fit the hold length and hatch openings with room for safe landing. Steel concentrates a great deal of weight on a small area, so the permissible tank-top load and the distribution of slabs between the holds are checked against the vessel’s loading documentation before nomination.
Stowage, dunnage, lashing and securing must suit heavy units that cannot be allowed to shift during the passage.
Vessel Crane Requirements
For individual pieces of up to 28 MT, the terms require four workable cranes with a minimum safe working load of 30 MT each and an outreach exceeding 9 metres. If a vessel offers cranes with a higher SWL, the maximum available safe lifting capacity is declared during nomination.
The margin shown is illustrative. Actual lifting margin and gear suitability are determined by Owners and the relevant technical parties.
Loading and Discharge Productivity
Loading at Paradip is agreed at 8,000 MT per weather working day, Sundays and holidays excluded unless used, basis four workable hooks and/or holds, pro rata if fewer are available. Discharge at Diliskelesi runs at the same rate, basis four workable geared holds, using the vessel’s cranes or shore cranes at Charterers’ option.
Because the rates are tied to the number of workable hooks, crane availability directly affects laytime and the final voyage cost.
Notice of Readiness
At the loading port, NOR is tendered during agreed office hours, Monday to Friday, excluding charter-party holidays; if the port is officially closed, NOR may only be tendered once operations resume.
At the discharge port, NOR may be tendered on arrival at the pilot station, harbour limits or another recognised waiting position, basis WIBON, WCCON, WIFPON and WIPON.
Laytime and Demurrage
A 24-hour turn time applies at Paradip; shifting, gangway, draft surveys, hatch inspection and customs formalities are excluded from laytime. At the discharge port, laytime commences at 08:00 on the next working day after valid NOR is accepted and ceases on completion of discharge.
Demurrage is agreed as a confidential daily rate, with despatch as per the charter party. On a 50,000 MT parcel, small differences in laytime wording translate into substantial differences in cost.
Crane Breakdown Risk
If one or more vessel cranes become unavailable, Owners have an agreed repair period, during which time counts in proportion to the workable cranes and holds. If repairs take longer, receivers may employ shore cranes, and the additional cost caused by the vessel’s crane failure is for Owners’ account.
Lightering and Shore Crane Costs
If the vessel cannot complete cargo operations directly at the berth because of draft, berth restrictions or gear limitations, lightering, barging, stevedoring at anchorage and floating or shore cranes can add substantial cost. The charter party allocates these costs in advance: here, costs arising from the vessel’s inability to complete the contractual discharge are for Owners’ account.
GENCON and Charter-Party Structure
Voyage charters for steel and other breakbulk cargoes are often based on the GENCON Charter Party for breakbulk and general cargo, with rider clauses for the cargo-specific terms. For slabs these cover gear and outreach, NOR and laytime, crane breakdown, lightering costs, freight payment and the war-risk and security costs included in the freight.
In this case freight is agreed in USD per metric ton basis routing via the Cape of Good Hope, payable in full after the Bill of Lading date and before breaking bulk.
Vessel Vetting and Compliance
The nominated vessel, Owners and relevant operating parties must comply with applicable US, EU and United Nations sanctions; a vessel or Owner on an applicable sanctions or SDN list would not be accepted. Further vetting may cover vessel age, flag, ITF status where applicable, GHG performance, RightShip requirements and previous trading history.
What Owners Need Before Quoting
Owners and operators quote faster and more accurately when the enquiry already states:
- total quantity and tolerance;
- maximum unit weight and dimensions of the slabs;
- loading and discharge ports and any berth restrictions;
- laycan;
- loading and discharge rates and terms;
- gear requirements: number of cranes, SWL and outreach.